How hours from an offer show in capacity

Modified on Wed, 25 Nov at 7:56 AM

This article explains how the hours in an offer show in Project Flow's capacity overview. In short, offer hours become estimated hours on the project's activities, and estimated hours don't count in capacity. Only hours you plan in the project plan, or on tasks, use capacity.

What happens to the offer hours

When you click Create project on an offer, or Connect to a project for an existing project, Project Flow copies the offer into the project:

  • Each activity on the offer becomes an activity on the project. Its Estimated hours (Estimerte timer) is the sum of the hours on that offer line.
  • With the Tasks module, the offer's tasks become tasks with their own estimated hours. The person in the offer's "Our reference" field becomes responsible for them.
  • The offer's responsible person is added to the project as project owner. The roles on the offer lines are not added as project members.
  • No hours are planned. The project plan, Reservations and Capacity show nothing for the project yet.

The new project gets the status set in Default project status for projects created from an offer (Standard prosjektstatus for prosjekt opprettet fra tilbud), under the offer settings. The default is In progress (Under arbeid).

Plan the hours so they use capacity

Capacity counts planned hours and absences, not estimated hours. To make the offer's hours show:

  1. Add the co-workers who will do the work to the project.
  2. Open the project's Project plan (Prosjektplan) and plan their hours per activity and week. Use the activity's estimated hours as a guide; the project plan chart shows them as Estimated hours on activities (Estimerte timer på aktiviteter).

The hours you plan in the project plan are the reservations. They show at once in Reservations (Reservasjoner), Resource planner (Ressursplanlegger) and Capacity (Kapasitet). Hours you plan on tasks are also added to the project plan for that co-worker, activity and day.

Read the hours in Capacity

Go to Co-workers (Medarbeidere) › Capacity (Kapasitet). You need the right permissions and the resource planning feature turned on for your company.

  • The filter Project status (Prosjektstatus) includes all statuses by default, also Offer (Tilbud).
  • The chart Assigned time per project state (Tildelt tid per prosjektstatus) splits the planned hours by project status, and by the probability set on the price model. For example, "Offer - 50%" shows hours on projects with the status Offer and a 50 % probability.

See expected work before the offer is accepted

To show work you expect to win, give the project the status Offer (Tilbud) and plan its hours. If projects created from offers should always start as Offer, change Default project status for projects created from an offer to Offer. Set a probability on the price model to see the hours weighted in Capacity.

Q&A

Q: I created a project from an accepted offer, but Capacity shows nothing.

A: The offer hours are estimated hours, not planned hours. Plan them in the project plan, or on tasks.

Q: The project is missing on the Reservations page.

A: By default, Reservations doesn't show projects with the status Finished or Offer rejected. Change the project status filter on the page.

Q: The co-workers from the offer lines are not on the project.

A: Only the offer's responsible person is added. Add the other co-workers to the project before you plan their hours.

Was this article helpful?

That’s Great!

Thank you for your feedback

Sorry! We couldn't be helpful

Thank you for your feedback

Let us know how can we improve this article!

Select at least one of the reasons
CAPTCHA verification is required.

Feedback sent

We appreciate your effort and will try to fix the article